Setting Up the Commissioning Schedule Manually

Previous Next

A schedule can be defined for each step in the Commissioning process and updated as each step is initiated and completed by uses with the required access permission. The Commissioning schedule defines start and finish dates for several types of schedules, including:

Baseline – initial schedule set
Baseline Late – revised baseline schedule to incorporate changes
Forecasted – expected schedule
Actual - A baseline schedule can be defined and compared to actual dates.

To set up a Commissioning schedule:

1.From the Commissioning Summary page, click the item for which you want to view standard issues. The Item Details page opens.
2.Click the Schedule tab. The Commissioning steps are listed with dates that can be set for each step.
3.To define a schedule, click the Calendar icon and select the date. The date displays.
4.Click the Save button.